2017 Bond Issue

Promises Made, Promises Kept

It’s summer in Michigan and that means our construction and building projects are underway. Thanks to the voter-approved Bond in 2017, we are able to continue much-needed upgrades and building maintenance. Our goal is to protect the community’s building assets and provide our students with a quality learning environment. We are currently in the second phase of the bond issue and listed below are the projects that we will be working on this summer.

Summer 2019 Projects by Building:

Ashley Elementary School
 

  • Pave main entrance parking lot
  • Install new windows
  • Remodel kitchen and install new equipment
  • Replace chiller
  • Upgrade unit ventilators

Great Oaks Elementary School
 

  • Upgrade playground area
  • Create new kick-ball play area
  • Replace roofing
  • Upgrade unit ventilators
  • Install new kitchen equipment
  • Install LED lighting fixtures in gym and cafeteria

Maconce Elementary School
 

  • Upgrade playground area
  • Replace roofing
  • Upgrade unit ventilators
  • Install new kitchen equipment
  • Install LED lighting fixtures in gym and cafeteria

Middle School South
 

  • Install new running track surface
  • Improve existing tennis courts
  • Install building message board
  • Replace roofing
  • Install new fascia panels
  • Replace flooring in classrooms
  • Replace interior doors and hardware
  • Install new kitchen equipment
  • Flooring and finish upgrade in Shoreliner
  • Upgrade HVAC controls system
  • Replace chiller
  • Install LED lighting fixtures in gym

Middle School North
 

  • Pave main entrance parking lot
  • Install new running track surface
  • Install building message board
  • Replace roofing
  • Upgrade athletic area buildings
  • Upgrade restrooms at athletic area
  • Replace flooring in classrooms
  • Replace interior doors and hardware
  • Paint gymnasium
  • Upgrade ceiling grid
  • Upgrade HVAC controls system
  • Install LED lighting fixtures in gym

Anchor Bay High School
 

  • Pave north student parking lot
  • Upgrade tennis courts
  • Upgrade fencing in athletic field areas
  • Upgrade drainage and landscaping at the lower level of athletic wing
  • Remodel EFIS panels between classroom windows
  • Replace flooring in main, counseling, and athletic offices
  • Upgrade tile and grout in sections of the commons and east side of the school
  • Upgrade main gym bleachers
  • Upgrade lighting and circuits
  • Upgrade theater

MacDonald Early Childhood Center/ Administration Office
 

  • Pave main entrance parking lot and bus loop
  • Pave north end parking area
  • Upgrade sewage lagoon system
  • Install LED lighting fixtures in gym and cafeteria

Early Childhood Center
 

  • Pave parking lot
  • Install dumpster pad and screen wall enclosure
  • Expand the playground area
  • Remodel main entrance
  • Replace interior doors and hardware

Transportation Building
 

  • Install LED lighting fixtures in the bus garage
  • Upgrade block heaters

Projects that have been completed:

 

  • Project Lead the Way (STEM) – Converted classrooms to Project Lead the Way (STEM) classrooms at Elementary Schools.
  • Purchased and installed STEM equipment in classrooms throughout the school district.
  • Technology – Purchased and installed 140 new teacher workstations for Lighthouse Elementary, Maconce Elementary, and Great Oaks Elementary schools.
  • Technology – Replaced the network at Anchor Bay High School, Middle School North, and Middle School South.
  • Transportation – Purchased six new school buses.
  • Aquatic Center – Replaced roof and vapor barrier in the pool area.
  • Aquatic Center – Purchase Pool Equipment – Upgraded chemical controller.

Project Updates:

May 2018 Update
June 2018 Update 
July 2018 Update
August 2018 Update

Projected Completed in Summer 2018 by Building:

Ashley Elementary School
 

  • Upgrade secure entry controls
  • Upgrade playground area
  • Replace roofing
  • Replace corridor flooring
  • Replace classroom flooring
  • Install new LED parking lot lighting

Great Oaks Elementary School
 

  • Upgrade secure entry controls
  • Replace roofing shingles on the original building
  • Upgrade kitchen equipment
  • Install new LED parking lot lighting

Lighthouse Elementary School
 

  • Upgrade secure entry controls
  • Upgrade playground area
  • Replace roofing
  • Upgrade kitchen equipment
  • Install new air conditioning configuration at District’s head-end room
  • Install new LED parking lot lights

Lottie Schmidt Elementary School
 

  • Upgrade secure entry controls
  • Upgrade playground area
  • Replace roofing
  • Upgrade kitchen equipment
  • Pave main entrance lot
  • Install new concrete walks under the covered entry
  • Install new flagpole and concrete pad
  • Remodel original building fascia panels
  • Install new dumpster enclosure
  • Replace vinyl tile flooring
  • Replace corridor flooring
  • Replace classroom flooring
  • Replace interior doors and frames
  • Install ADA hardware
  • Install new LED parking lot lights

Maconce Elementary School
 

  • Upgrade secure entry controls
  • Replace roofing
  • Upgrade kitchen equipment
  • Install new LED parking lot lights

Naldrett Elementary School
 

  • Upgrade secure entry controls
  • Upgrade playground area
  • Replace roofing
  • Replace original laminate doors and frames
  • Install ADA hardware
  • Replace HVAC equipment
  • Install LED lighting fixtures in gym
  • Install new LED parking lot lights

Sugarbush Elementary School
 

  • Upgrade secure entry controls
  • Upgrade playground area
  • Replace roofing
  • Upgrade kitchen equipment
  • Pave service drive
  • Upgrade fascia panels
  • Install new dumpster enclosure
  • Replace VCT flooring
  • Replace corridor flooring
  • Replace classroom flooring
  • Replace interior doors and frames
  • Install ADA door hardware
  • Remodel staff restrooms
  • Install new LED parking lot lights

Middle School South
 

  • Upgrade secure entry controls
  • Upgrade kitchen equipment
  • Install new LED parking lot lighting

Middle School North
 

  • Upgrade secure entry controls
  • Upgrade kitchen equipment
  • Install new LED parking lot lighting

Anchor Bay High School
 

  • Upgrade secure entry controls
  • Install synthetic turf at Stadium Field
  • Install new building sign
  • Install new running track surface
  • Install video scoreboard and sound system at Stadium Field
  • Install new fencing at athletic field areas
  • Upgrade drainage and landscaping at lower level of athletic wing
  • Install new LED parking lot lighting

Aquatic Center
 

  • Site grading/drainage improvements
  • Replace roofing
  • Re-key exterior doors
  • Install epoxy coating on the locker room floor
  • Remodel locker room to provide a family changing room
  • Install shower partitions
  • Upgrade door hardware
  • Replace boilers
  • Replace rooftop heating/air conditioning unit
  • Replace men’s and women’s locker room fixtures
  • Upgrade interior lighting and circuitry (including occupancy sensors)
  • Upgrade to LED lighting in pool area
  • Install new LED parking lot lighting
  • Upgrade fire safety devices
  • Purchase pool equipment
  • Purchase technology equipment

MacDonald Early Childhood Center / Administration Office
 

  • Install new LED parking lot lighting

Early Childhood Center
 

  • Upgrade secure entry controls
  • Install new LED parking lot lights